Build times: Sling Aircraft Sling 4

Phoenix FS

Total Build Time
601 hours

Avionics

Build time: -

not started
0%

Firewall forward

Build time: 56 hours

not started
0%

Engine

Build time: -

not started
0%

Fuselage

Build time: 53 hours

not started
0%

Miscellaneous

Build time: 30 hours

not started
0%

Canopy

Build time: 30 hours

not started
0%

Electrical

Build time: -

not started
0%

Painting

Build time: -

not started
0%

Upholstery

Build time: -

not started
0%

Tail

Build time: 169 hours

not started
0%

Elevator

Build time: 72 hours

not started
0%

Horizontal stabilizer

Build time: 52 hours

not started
0%

Rudder

Build time: 32 hours

not started
0%

Vertical stabilizer

Build time: 13 hours

not started
0%

Wings

Build time: 293 hours

not started
0%

Ailerons

Build time: 44 hours

not started
0%

Flaps

Build time: -

not started
0%

Main wing

Build time: 48 hours

not started
0%

Spar

Build time: 30 hours

not started
0%

Section build times

Section Status Time
(hrs)
Progress
Avionics not started - -
Firewall forward not started 56 -
Engine not started - -
Fuselage in progress 53 -
Miscellaneous not started 30 -
Canopy not started 30 -
Electrical not started - -
Painting not started - -
Upholstery not started - -
Tail not started 169 -
Elevator not started 72 -
Horizontal stabilizer not started 52 -
Rudder not started 32 -
Vertical stabilizer not started 13 -
Wings not started 293 -
Ailerons not started 44 -
Flaps not started - -
Main wing not started 48 -
Spar not started 30 -
* If a parent section's time is greater than the sum of its sub-sections, it simply means one or more posts weren't categorized under a sub-section.

Build times by tag

Tag Build time (hrs)
vertical stabilizer 9
rudder 26
left 42
horizontal stabilizer 52
Elevator 58
Wing 114
Fuselage 10
fuel system 30
canopy -
Priming 63
Landing Lights 40
Deburring 48
Ribs 24
Seats 10
Undercarriage 62
Wheels 30
Wing Spars 30
Forward Fuselage -
Inside Wings 110
Flaps, Ailerons, Wing and Aileron Tips 68
Wing Fuel Tanks 50
Trim tab 24
Landing gear 62
Window 20
Cleaning 4
rib 12
rib 4 12
rib 5 12
rib 6 12
rib 12 42
rib 8 50
issue 12
rib 9 8
Servo 24
Wings 105
Nose wheel 62
Main landing gear 42
Motor mount 30
right wing 100
Bottom skins 20
Seat 10
taxi lights 40
taxi light 40
landing light 40
leading edge 40
left wing 30
pitot -
front seats 10
throttle -
breaks -
canop 20
windows 20
glass 20
fuel tank 20
wingtip 20

Build times by week