Empennage delivery and inventory
We took delivery of our empennage kit and began inventory. We only had a single screw unaccounted for up front and then about a year later we discovered that one of our bags of 76 nut plates was the wrong part number. One of our bags of parts was backordered which drove our decision on which parts to start building.




Logan was dying to use that crowbar

Big bag of rivets, bolts, screws, and other assorted hardware


Extremely well done packing job by Vans

I wound up later on redoing this to where I just put all the skins up top so I had unfettered access to the parts. It was organized the same way a tail number bin was when I worked on vipers.


pneumatic lines, coax, control cables