Build times: Bearhawk Aircraft 4 Place

Neville's Bearhawk

Total Build Time
1729.7 hours

Avionics

Build time: 41 hours

complete
100%

Firewall forward

Build time: 444 hours

complete
100%

Engine

Build time: 254.5 hours

complete
100%

Fuselage

Build time: 530.8 hours

complete
100%

Miscellaneous

Build time: 72.5 hours

complete
100%

Electrical

Build time: -

complete
100%

Painting

Build time: 32 hours

complete
100%

Upholstery

Build time: 40.5 hours

complete
100%

Tail

Build time: 167 hours

complete
100%

Elevator

Build time: 16 hours

complete
100%

Horizontal stabilizer

Build time: 41 hours

complete
100%

Rudder

Build time: 54.5 hours

complete
100%

Vertical stabilizer

Build time: 55.5 hours

complete
100%

Wings

Build time: 409.8 hours

complete
100%

Ailerons

Build time: 24 hours

complete
100%

Flaps

Build time: 169.3 hours

complete
100%

Main wing

Build time: 56.5 hours

complete
100%

Section build times

Section Status Time
(hrs)
Progress
Avionics in progress 41
100%
Firewall forward in progress 444
100%
Engine in progress 254.5
100%
Fuselage in progress 530.8
100%
Miscellaneous complete 72.5
100%
Electrical complete -
100%
Painting complete 32
100%
Upholstery in progress 40.5
100%
Tail complete 167
100%
Elevator complete 16
100%
Horizontal stabilizer complete 41
100%
Rudder complete 54.5
100%
Vertical stabilizer complete 55.5
100%
Wings complete 409.8
100%
Ailerons complete 24
100%
Flaps complete 169.3
100%
Main wing complete 56.5
100%
* If a parent section's time is greater than the sum of its sub-sections, it simply means one or more posts weren't categorized under a sub-section.

Build times by tag

Tag Build time (hrs)
Undercarriage 25
Trim 6
Floor 18.6
Horizontal Stabilizer and Elevator 11
Trim tab 5
Inspection ports 1.5
Seats 25.6
Control assembly 28.5
Window 5.5
Boot cowl 94
Aerial 1
Nose bowl 6
Cockpit - Instrument Panel and Controls 18
Horizontal Stabilizer and Elevators 12
Nutplates 2
Forward Fuselage 9
engine 26
empennage 8
brakes 47.3
Cowls 50
Dimpling 11
Covering 110
Instrument Panel 72
firewall 16.5
NACA vents 4.5
Fuel Lines and Valve Installation 30
Doors 138
Skylight 26
Paint 112.5
Baffles 31
cowl 3
rudder 26
Vertical Stabilizer and Rudder 10
Flying -
Firewall Forward 111
Landing gear 4
avionics 70
propeller 10
Fabrication of parts 3
Elevator 19
Tunnel 14
horizontal stabilizer 3
Wing 7
Stringers 12.2
Wheels 15
Welding 6
Match Drilling 5
exhaust 19
Cargo 5
Elt 6
flaps 13.8
fuel system 25.8
Rough Assembly 5
Upholstery 7
Aft Fuselage 0.5
Door sill 6
Fuselage 2

Build times by week