Tyler's Sling TSi

Day 41

Center Fuselage Joiner & Floor Frame

Today was lots of fun. We began assembling the Center Fuselage Joiner and floor frame. Lots of brackets to be Cleco’ed and riveted taking care of proper orientation. Many of the rivets had to be hand pulled because of how tight some of the areas were, but everything is going together very nicely. Should be able to finish the frame up tomorrow and begin riveting the floor skin on.